Last week was a big week for the debris crew as they finished clearing the footprint of the bridge. The final obstruction that was at bent 12, drill shaft 1201, was removed. The final outer casing was set at shaft 1201 on Thursday, March 25. This week, the project team continues to pour the traffic rail on the bridge deck and has completed bent 11 drill shafts. Bent 11 columns were poured on Monday, April 1 and all the casings are set in the remaining 6 shafts in the water. Bent ...